CONTRACT NAME – RENOVATION OF STORES BUILDING AT KOLONNAWA – WPS11

CLIENT – CEYLON ELECTRICITY BOARD

LOCATION – KOLONNAWA

DURATION – 06 Months

YEAR OF COMPLETION – 26.01.2023

CONTRACT VALUE – Rs. 47,323,995.00

IMG-20250626-WA0009
IMG-20250626-WA0010
Exit full screenEnter Full screen
previous arrow
next arrow
IMG-20250626-WA0009
IMG-20250626-WA0010
previous arrow
next arrow

CONTRACT NAME – RELOCATING THE R&D BRANCH OF CEB AT KOLONNAWA CENTRAL STORES
PREMISES

CLIENT – CEYLON ELECTRICITY BOARD

LOCATION – KOLONNAWA

DURATION – 03 Months

YEAR OF COMPLETION – 30.03.2021

CONTRACT VALUE – Rs. 25,768,058.60

IMG-20220603-WA0010
IMG-20220603-WA0012
IMG-20220603-WA0017
IMG-20220603-WA0013
IMG-20220603-WA0019
Exit full screenEnter Full screen
previous arrow
next arrow
IMG-20220603-WA0010
IMG-20220603-WA0012
IMG-20220603-WA0017
IMG-20220603-WA0013
IMG-20220603-WA0019
previous arrow
next arrow

CONTRACT NAME – CONSTRUCTION OF TWO STORED BUILDING FOR CONSUMER SERVICE CENTRE STAGE 1

CLIENT – CEYLON ELECTRICITY BOARD

LOCATION – DELGODA

DURATION – 150 DAYS

YEAR OF COMPLETION – 16.03.2015

CONTRACT VALUE – Rs. 15,207,633.50

77t764435422545
20150615_114039
20160209_094130
Exit full screenEnter Full screen
previous arrow
next arrow
77t764435422545
20150615_114039
20160209_094130
previous arrow
next arrow

CONTRACT NAME – CONSTRUCTION OF NEW BUILDING FOR CONSUMER SERVICE CENTRE

CLIENT – CEYLON ELECTRICITY BOARD

LOCATION – HORANA

DURATION – 05 MONTHS

YEAR OF COMPLETION – 26.06.2014

CONTRACT VALUE – RS.13, 996,518.10

DSCF0833-1024x683
DSCF0855
DSCF0873
Exit full screenEnter Full screen
previous arrow
next arrow
DSCF0833-1024x683
DSCF0855
DSCF0873
previous arrow
next arrow

CONTRACT NAME – CONSTRUCTION OF NEW BUILDING FOR CONSUMER SERVICE CENTRE 

CLIENT –  CEYLON ELECTRICITY BOARD

LOCATION – INGIRIYA

DURATION – 150 CALENDAR DAYS

YEAR OF COMPLETION – 28.07.2013

CONTRACT VALUE –  RS. 11,190,702.27

DSCF2388
DSCF2367
DSCF2367
DSCF2395
DSCF2392
DSCF2379
DSCF2373
Exit full screenEnter Full screen
previous arrow
next arrow
DSCF2388
DSCF2367
DSCF2367
DSCF2395
DSCF2392
DSCF2379
DSCF2373
previous arrow
next arrow

CONTRACT NAME – RENOVATION OF KITCHEN BASE HOSPITAL

CLIENT – MINISTRY OF HEALTH

LOCATION – MULLAERIYAWA

DURATION – 154 DAYS

YEAR OF COMPLETION – 28.06.2013

CONTRACT VALUE – RS.6,691,594.5

P1050185
P1050187
P1050190
P1050192
P1050195
P1050197
P1050200
P1050197
Exit full screenEnter Full screen
previous arrow
next arrow
P1050185
P1050187
P1050190
P1050192
P1050195
P1050197
P1050200
P1050197
previous arrow
next arrow

CONTRACT NAME – CONSTRUCTION OF GENERATOR ROOM AT AITKEN SPENCE LOGISTICS YARD

CLIENT – ACE CONTAINERS (PVT) LTD

LOCATION – WATTALA

DURATION – 02 MONTHS

YEAR OF COMPLETION – 28.12.2012

CONTRACT VALUE – RS.3,353,629.50

P1050203
P1050205
Exit full screenEnter Full screen
previous arrow
next arrow
P1050203
P1050205
previous arrow
next arrow

CONTRACT NAME – RENOVATION OF THALANGAMA CONSUMER SERVICE CENTRE

CLIENT – CEYLON ELECTRICITY BOARD

LOCATION – THALANGAMA

DURATION – 300 Days

YEAR OF COMPLETION – 10.09.2012

CONTRACT VALUE – RS. 8,417,781.38

IMG_2435
IMG_2401
IMG_2411
IMG_2424
Exit full screenEnter Full screen
previous arrow
next arrow
IMG_2435
IMG_2401
IMG_2411
IMG_2424
previous arrow
next arrow

CONTRACT NAME – BALANCE WORKS OF CLUB HOUSE & SWIMMING POOL (ADDITIONAL WORKS 01& 02)

CLIENT – FINANCE & GUARANTEE COMPANY LTD

LOCATION – THALAHENA

DURATION – 06 MONTHS

YEAR OF COMPLETION – 10.12.2009

CONTRACT VALUE – RS. 36,117,224.40

IMG_0008
IMG_0004
IMG_0012
IMG_0013
Exit full screenEnter Full screen
previous arrow
next arrow
IMG_0008
IMG_0004
IMG_0012
IMG_0013
previous arrow
next arrow

CONTRACT NAME – PROPOSED IMPROVEMENTS TO ENTRANCE LOBBY AND AUDITORIUM – STAGE I FOR NATIONAL SCIENCE FOUNDATION

CLIENT – NATIONAL SCIENCE FOUNDATION, COLOMBO 07

LOCATION – COLOMBO 07

DURATION – 03 MONTHS

YEAR OF COMPLETION – 11.12.2008

CONTRACT VALUE – Rs.4,267,211.14

IMG_0014
IMG_0014a
Exit full screenEnter Full screen
previous arrow
next arrow
IMG_0014
IMG_0014a
previous arrow
next arrow

CONTRACT NAME – CONSTRUCTION OF LOT 94,73,72,71 

CLIENT – FINANCE & GUARANTEE COMPANY LTD

LOCATION – THALAHENA

DURATION – 09 MONTHS

YEAR OF COMPLETION – 07.03.2008

CONTRACT VALUE – RS.33, 291,875.16

IMG_0010
IMG_0009
Exit full screenEnter Full screen
previous arrow
next arrow
IMG_0010
IMG_0009
previous arrow
next arrow

CONTRACT NAME – CONSTRUCTION OF TWIN HOUSES FOR PROPOSED CONTINENTAL RESIDENCIES 

CLIENT – FINANCE & GUARANTEE COMPANY LTD

LOCATION –  NEGOMBO

DURATION – 07 MONTHS

YEAR OF COMPLETION – 10.04.2007

CONTRACT VALUE – RS. 22,608,504.85

PENTAX Image
001 (2)
PENTAX Image
PENTAX Image
PENTAX Image
Exit full screenEnter Full screen
previous arrow
next arrow
PENTAX Image
001 (2)
PENTAX Image
PENTAX Image
PENTAX Image
previous arrow
next arrow

CONTRACT NAME – CONSTRUCTION OF HOUSES FOR PROPOSED CONTINENTAL RESIDENCIES 

CLIENT – FINANCE & GUARANTEE COMPANY LTD   

LOCATION –  NEGOMBO

DURATION – 07 MONTHS

YEAR OF COMPLETION – 10.04.2007

CONTRACT VALUE – RS. 22,608,504.85

SCAN 10
SCAN 11
SCAN 12
Exit full screenEnter Full screen
previous arrow
next arrow
SCAN 10
SCAN 11
SCAN 12
previous arrow
next arrow

CONTRACT NAME – CONSTRUCTION OF SAMSUNG SHOWROOM AT T. B. JAYAH MAWATHA

CLIENT – MS SINHAGIRI LTD

LOCATION –  COLOMBO 10

DURATION – 06 MONTHS

YEAR OF COMPLETION – 10.12.2004

CONTRACT VALUE – RS. 10,310,247.00

001 (5)
Exit full screenEnter Full screen
001 (5)
previous arrow
next arrow

CONTRACT NAME – CONSTRUCTION OF POST OFFICE & PM QUARTERS 

CLIENT – DEPARTMENT OF BUILDINGS

LOCATION – MODARA

DURATION – 03 MONTHS

YEAR OF COMPLETION – 24.03.2000

CONTRACT VALUE – RS. 2,997,878.40

001 (3)
Exit full screenEnter Full screen
001 (3)
previous arrow
next arrow

CONTRACT NAME – CONSTRUCTION OF HOUSES FOR PROPOSED ROLAND PARK 

CLIENT – CEYLINCO   

LOCATION –  JAELA

DURATION

YEAR OF COMPLETION

CONTRACT VALUE

21
31
38
Exit full screenEnter Full screen
previous arrow
next arrow
21
31
38
previous arrow
next arrow

CONTRACT NAME – CONSTRUCTION OF HOUSES

CLIENT – CEYLINCO   

LOCATION –  MIRIHANA

DURATION

YEAR OF COMPLETION

CONTRACT VALUE

scan 4
scan 3
scan 5
Exit full screenEnter Full screen
previous arrow
next arrow
scan 4
scan 3
scan 5
previous arrow
next arrow

CONTRACT NAME – CONSTRUCTION OF 2×10 MVA WATTALA PRIMARY SUBSTATION CIVIL WORKS

CLIENT – CEYLON ELECTRICITY BOARD

LOCATION – WATTALA

DURATION – 06 MONTHS

YEAR OF COMPLETION – 27.02.2002

CONTRACT VALUE – RS. 7,990,643.90

001 (7)
Exit full screenEnter Full screen
001 (7)
previous arrow
next arrow

<<1.  2.  3.>>